July 10, 2008
Front Stairway Landings Installed

   

200-lb. steel deck frame is hand-carried in through front door.
200-lb. steel deck frame is hand-carried in through front door.

Frame is placed on plank ramp leading up to scaffold in stairwell.
Frame is placed on plank ramp leading up to scaffold in stairwell.

Frame is blocked to specified height, leveled and positioned for bolting to wall with spacers.
Frame is blocked to specified height, leveled and positioned for bolting to wall with spacers.

Upper mid-landing frame is completed with deck-support plates, lower mid-landing frame is positioned for installation.
Upper mid-landing frame is completed with deck-support plates, lower mid-landing frame is positioned for installation.

Upper hall floor is cut back to let landing match size of main floor hall landing.
Upper hall floor is cut back to let landing match size of main
floor hall landing.

Upper floor joist is removed to create opening for stair installation.
Upper floor joist is removed to create opening for stair installation.


Return to Old School House Transformation Diary